Shoring Design Calculations: What Goes Into Excavation Support

Shoring design calculations are the engineering analyses showing that a temporary excavation support system (soldier piles and lagging, sheet piles, a braced or tied-back wall, or a shaft) can resist soil, groundwater and surcharge loads at every construction stage without failing or moving enough to damage adjacent structures. They turn geotechnical data into earth pressures, size each member, set the embedment depth, and check bottom stability, seepage and deflection.

Inputs: what the calculations start from

  • Geotechnical report: soil and rock layers, unit weights, drained strength (φ′, c′), undrained shear strength (Su) for clays, and obstructions such as boulders that affect driving or drilling.
  • Groundwater: design water level, including seasonal highs, and permeability. It decides whether the wall must be watertight or the site dewatered.
  • Surcharges: traffic, cranes, excavators, stockpiles, rail and adjacent footings. A uniform surcharge q adds a lateral pressure K·q; line, strip and point loads are distributed with Boussinesq-type elastic solutions. Caltrans, for example, requires a lateral construction surcharge of 72 psf over at least the upper 10 feet of retained soil.
  • Site constraints: geometry, duration, utilities, property lines (which decide whether tiebacks are possible) and the movement neighbors can tolerate.

Lateral earth pressure

Pressure depends on wall movement. Active pressure develops when the wall moves away from the soil enough to mobilize its strength; at-rest pressure applies when the wall barely moves; passive resistance develops where the embedded wall pushes into the soil.

  • Rankine (frictionless vertical wall, level ground): Ka = tan²(45° − φ′/2), Kp = tan²(45° + φ′/2).
  • Coulomb adds wall friction and sloping ground. With significant wall friction, log-spiral passive coefficients (such as Caquot–Kérisel) are preferred, because Coulomb’s planar surface overestimates passive resistance.
  • At rest: K0 ≈ 1 − sin φ′ (Jaky) for normally consolidated soils, often used for stiff walls next to sensitive structures.

Apparent pressure envelopes for braced excavations

For walls with struts or anchors, Terzaghi and Peck’s empirical envelopes, derived from measured strut loads, replace the triangular diagram. For sands the envelope is a uniform 0.65·Ka·γ·H; for clays it depends on the stability number γH/Su. FHWA GEC No. 4 uses trapezoidal envelopes for anchored walls. They estimate support loads, not actual pressures; water pressure and surcharges are added separately.

Choosing the shoring system

Typical applications and governing checks:

System Typical use Governing checks
Soldier piles and lagging Soils with stand-up time, above groundwater or dewatered Pile bending, embedment, lagging
Steel sheet piles Soft or water-bearing soils, cofferdams, drivable ground Section modulus, embedment, seepage
Braced (strutted) Narrow cuts and shafts, or no room for anchors Strut and wale loads, buckling
Tied-back Wide excavations needing open working space Anchor capacity, pile axial load, global stability
Secant pile or diaphragm wall Deep excavations, high groundwater, sensitive neighbors Stiffness, water cut-off, base stability
Shafts Launch and reception shafts, pump stations Ring compression, openings, jacking reaction

For shallow utility trenches, manufactured trench shields and hydraulic shoring used within their tabulated data are common alternatives.

Member checks

Soldier piles and lagging

Above subgrade, each pile carries the pressure over one pile spacing. Below subgrade, soil arching widens the passive zone: the Caltrans Trenching and Shoring Manual allows up to 3 times the effective pile width in granular soils and 2 times in cohesive soils, never more than the spacing. Piles are checked for bending, shear and, on anchored walls, the vertical component of anchor loads. Where arching can develop, Caltrans allows lagging to be designed for 0.6 times the shoring design pressure.

Sheet piles

Section modulus follows from the maximum moment and steel grade, with checks on drivability and, where piles remain in place, corrosion. The USS Steel Sheet Piling Design Manual covers cantilever and anchored walls, including the free-earth-support method.

Wales, struts and tiebacks

Wales are continuous beams checked for bending, shear and web crippling at supports. Struts are checked for buckling, self-weight bending and temperature load; preloading reduces movement. Tieback loads come from the apparent pressure diagram. The bond zone must lie behind the critical failure surface, with minimum unbonded lengths commonly 15 feet for strand and 10 feet for bar. Every production anchor is proof tested and a share are performance tested, to a test load set by the specifications: 1.33 times the design load is common for permanent anchors, while FHWA GEC No. 4 notes that 1.2 is commonly used for temporary ones.

Shafts

Circular shafts carry pressure mainly in ring compression, though uneven loading still causes bending. Launch shafts need a thrust wall that transfers jacking forces into the soil, and both launch and reception shafts need framing around the tunnel eye.

Embedment depth for cantilever walls

A cantilever wall depends entirely on passive resistance. Moments are balanced about a rotation point at depth D0 below subgrade; the Caltrans simplified method then sets D = 1.2·D0 (citing AASHTO LRFD 3.11.5.6) and notes that this increase is not a factor of safety. Safety is added through a minimum resisting-to-driving moment ratio (a Caltrans example uses 1.3), a reduced passive coefficient, or LRFD or Eurocode partial factors. Since moment grows roughly with the cube of retained height, cantilevers suit moderate depths.

Deflection and adjacent structures

Movements are estimated with empirical correlations (Peck, 1969; Clough and O’Rourke, 1990) or with subgrade-reaction or finite element models; in France, the subgrade-reaction model of NF P94-282 is widely used alongside limit-equilibrium methods. Predicted settlements are compared with building tolerance, often through angular distortion and lateral strain (Boscardin and Cording, 1989). Remedies include more support levels, preloading, at-rest design, a stiffer wall or underpinning. OSHA restricts excavation below adjacent footings, where it could endanger employees, unless underpinning is provided, the excavation is in stable rock, or a registered professional engineer approves (29 CFR 1926.651(i)).

Basal heave, bottom stability and seepage

In soft clay, the soil beside the cut can push the bottom up. Basal heave is checked with the Terzaghi or Bjerrum and Eide methods, comparing Nc·Su with γH + q (Caltrans recommends a factor of safety of at least 1.5); if the margin is too low, the wall is extended into a stiffer layer or the cut is excavated in sections. In sand below the water table, upward seepage at the wall toe can cause piping when the exit gradient nears the critical value γ′/γw, about 1.0; seepage analysis sets the cut-off depth or dewatering. Where clay overlies a confined aquifer, the remaining soil plug must outweigh the uplift pressure. Global stability is checked with limit-equilibrium methods.

Staged construction: excavation and removal

Each stage is analyzed, because peak moments can occur at an intermediate stage or during removal:

  1. Excavate to just below the first support level (cantilever stage).
  2. Install and preload struts or lock off anchors; repeat down to subgrade.
  3. Build the permanent structure, then remove or transfer supports in the specified order, checking every intermediate condition.

OSHA requires removal to start at the bottom of the excavation, with backfilling progressing together with removal; in trenches, excavating up to 2 feet below the bottom of the support members is allowed only if the system is designed for the full depth and shows no soil loss (29 CFR 1926.652(e)).

Monitoring

Survey points, inclinometers, strut and anchor load cells, piezometers, crack gauges and vibration monitors verify design assumptions against thresholds such as review, alert and stop levels. OSHA also requires a competent person to inspect excavations and protective systems daily before work starts and after every rainstorm (29 CFR 1926.651(k)).

Codes, standards and manuals

  • OSHA 29 CFR 1926 Subpart P: workers must be protected from cave-ins unless the excavation is entirely in stable rock, or is less than 5 feet deep and a competent person finds no indication of a potential cave-in. OSHA’s sloping, timber and aluminum hydraulic shoring tables stop at 20 feet. Excavations deeper than 20 feet require a protective system designed by a registered professional engineer (or PE-approved tabulated data); the design must be in writing, with a copy at the jobsite.
  • Caltrans Trenching and Shoring Manual (July 2025 revision).
  • AASHTO LRFD Bridge Design Specifications, Sections 3 and 11.
  • FHWA GEC No. 4, Ground Anchors and Anchored Systems, and PTI DC35.1.
  • USS Steel Sheet Piling Design Manual.
  • EN 1997-1 (Eurocode 7) with national annexes; in France, NF P94-282 for embedded walls. The second generation (EN 1997-1:2024, EN 1997-3:2025) is being phased in.

OSHA defines a registered professional engineer as one registered in the state where the work is performed, although a PE registered in any state may approve manufactured protective systems or tabulated data used in interstate commerce (29 CFR 1926.650(b)); project specifications state who seals the calculations.

Frequently asked questions

When does shoring need to be designed by a professional engineer?

Under OSHA Subpart P, an excavation deeper than 20 feet needs a protective system designed by a registered professional engineer or taken from tabulated data approved by one. Owners, agencies and railroads often require sealed shoring calculations at shallower depths, especially next to roads, tracks or buildings.

What is the difference between active, at-rest and passive earth pressure?

Active pressure is the lowest pressure soil exerts once the wall moves away from it; at-rest pressure applies when the wall does not move; passive resistance is the highest resistance the soil offers when the wall pushes into it. Shoring designs apply active or at-rest pressure behind the wall and a factored passive resistance below subgrade.

How is the embedment depth of a cantilever shoring wall calculated?

Driving and resisting moments are balanced about a rotation point below subgrade to find a depth D0, which the simplified method increases by 20 percent. A factor of safety or partial factors are then applied as the governing manual or code requires.

Can soldier piles and lagging be used below the water table?

Not without groundwater control, because lagging is not watertight and saturated sands or silts can flow through the gaps. Caltrans considers lagging questionable in soft clays and in silts or clayey sands below the water table; sheet piles, secant piles or dewatering are the usual alternatives.

What should a shoring calculation package include?

Design criteria and references, soil and groundwater parameters, load diagrams for each stage, member and embedment checks, stability and deflection checks, and the installation and removal sequence. Drawings and monitoring thresholds complete the package.

FreXetude, an engineering firm based in Paris, prepares structural calculations, shoring and shaft designs (sheet piles, soldier-pile walls, launch and reception shafts) and construction documents for projects in France and the United States. You can review our engineering services or send us your project details to receive a quote within one business day.